Dunbar Landfill, East Lothian

Viridor Waste Management Ltd
Contract value:

Capabilities:
Waste Remediation & Facilities Waste remediation & facilities

The project was primarily to enable existing gas wells to continue extracting gas, whilst having the ability to incorporate pneumatic pumps to assist with leachate control.

  • Installation of a temporary manifold, surface laid 90mm lateral gas connections and associated connections to four recently drilled gas wells in the current live tipping area of the landfill
  • Installation of 125mm gas extraction main with associated control valves and chambers
  • Supply and installation of pumped well heads to five wells in the restored area of the landfill, with associated buried air and condensate connections
  • Supply and installation of pumped well heads to two existing small diameter wells within the restored area, with associated buried air and condensate connections
  • Installation of air and condensate discharge lines to facilitate the future fitting of pneumatic pumps in the small diameter wells

Work was completed in July 2011, on schedule.